Clearwater Structures Inc. has completed a vast array of diverse jobs since our establishment in 2005. Some recent notable completed projects include:
MTO 2015-2016 - Lynde Creek & Nonquon Bridge , Hwy 7A/12
Structure Replacement at Lynde Creek Bridge - Includes removal of existing structure in stages, installation of new girders, concrete deck, sidewalks, barrier walls, approach slab & bridge deck waterproofing. Structure Rehabilitation at Nonquon Bridge - Includes saw cutting existing barrier walls, demolition of ballast walls & approach slabs to facilitate construction of semi-integral deck end.
Approximate Contract Value: $2,000,000
Subcontractor to Breannan Paving and Construction Ltd.
Completion February 2017
MTO 2015-2038 - Bridge Rehabilitation at Hwy 58, St. David's Rd. Interchange
Rehabilitation of 3 bridges in 2 stages. Concrete removal and concrete placement for ballast walls, wing walls deck ends, barrier walls, concrete overlay and approach slabs. Jacking and replacement of bearings.
Approximate Contract Value: $4,700,000
Completion December 2016
Concrete rehabilitation including: Jacking / Bearing replacement, concrete overlay, reconstruct abutments to semi-integral configuration.
Approximate Contract Value: $700,000
Completion: 2016
Jacking of six bridges at Hwy 400 and Hwy 401 interchange, including temporary support towers
Approximate Contract Value: $1,200,000
Subcontractor to Brennan Paving and Construction Ltd.
Completion: 2016
CCTV Inspection, Clean out of Catch Basins, Traffic Control, Portable Variable Message Signs, Ditch Clean out.
Approximate Contract Value: $3,000,000
Completion: August 2016
Construction of Dam Lock #37, Concrete & Reinforcing Steel, Dam Foundation, Foundation Slab, Piers, Sluiceways, Spillways, Headwalls, Abutments, Cut-off Walls, Stability Wall, Buttress, Retaining Wall, Concrete Steps & Apron, Concrete Crib Foundation, Wood Decking, Concrete Repair.
Approximate Contract Value: $7,000,000
Subcontractor to Metric Contracting Services
Completion: January 2016
Highbury Avenue Bridge Rehabilitation over CN Rail
Approximate Contract Value: $3,200,000
Completion: November 2015
Concrete rehabilitation of the existing Victoria St. Underpass at Hwy 401. Removals: Full depth removal of the bridge median, overhangs, sidewalk, approach slabs, deck ends, ballast wall and wing walls. Partial depth removals at the abutments, piers and soffit. Reconstruction of the new concrete median, approach slabs, wing walls, deck end extension, barrier walls, sidewalk on deck, and Jacking to replace bearings.
Approximate Contract Value: $14,000,000
Completion October 2015
Concrete test trail including, resealing of joints in concrete pavement, removal of concrete pavement (partial depth), traffic control signing, pavement marking, abrasive blast cleaning for overlays, place concrete overlays, finish/cure concrete overlays.
Approximate Contract Value: $150,000
Completion: August 2015
Roadway protection, electrical work, traffic control, restoration, protection/relocation of existing utilities, survey, dewatering, and concrete rehabilitation.
Approximate Contract Value: $3,800,000
Subcontractor to R.W. Tomlinson
Completion: January 2015
Saw cutting, concrete demolition, cleaning, reinforcing and restoring the deteriorated steel anchor section at the top of bridges 11 and 21.
Approximate Contract Value: $200,000
Completion: November 2014